1 · Welding line: what is unplanned downtime costing?
A robotic welding cell runs two shifts. The maintenance lead has six months of breakdown records and needs to put a number in front of the plant manager.
| Input (6 months) | Value |
|---|---|
| Planned production time | 1,920 h |
| Breakdowns | 24 |
| Total repair time | 96 h |
| Cost of a stopped line | $8,000 / h |
(1,920 − 96) ÷ 24 = 76.0 h96 ÷ 24 = 4.0 h76.0 ÷ (76.0 + 4.0) = 95.00%Downtime cost over the period: 96 h × $8,000 = $768,000.
What-if: if a preventive programme cut breakdowns to 15 and faster diagnosis brought MTTR to 3 h, MTBF becomes 125.0 h, availability 97.66%, and downtime cost $360,000 — a difference of $408,000 to weigh against the programme's cost.
2 · Aircraft component: mission reliability and spares
An operator flies a fleet with a line-replaceable unit whose field MTBF is known. Two questions: how likely is the unit to survive a typical flight, and how many spares should be held while repairs are away?
| Input | Value |
|---|---|
| Unit MTBF | 4,000 flight hours |
| Typical mission | 10 h |
| Fleet | 20 aircraft × 250 FH / month |
| Repair turnaround (lead time) | 2 months |
| Spares fill-rate target | 95% |
R(10 h) = e^(−10 ÷ 4,000) = 99.75%5,000 FH / month ÷ 4,000 = 1.25 per month1.25 × 2 = 2.50 unitsThe smallest stock s with P(demand ≤ s) ≥ 95% is 5 spares, covering 95.8% of lead-time demand.
3 · Hospital imaging: turning an availability target into a repair deadline
A radiology department commits to 98% availability for a CT scanner. Its failure history gives an MTBF of 600 scheduled hours. The biomedical team needs to know how fast repairs must be to hit the target.
MTTR ≤ MTBF × (1 − A) ÷ A = 600 × 0.02 ÷ 0.98 = 12.2 hThe current service contract averages 18 h to restore, giving 97.09% — below target, and about 2.4 lost hours in an 84-hour scanning week. The requirement to put in the contract is a restore time of no more than 12 hours.
ToolsAvailabilityMTTR
4 · Data centre: what does a redundant UPS module buy?
A single UPS module has an availability of 99.9%. The facility is deciding whether to add a second module in parallel so either one can carry the load.
| Configuration | Availability | Expected downtime / year |
|---|---|---|
| Single module | 99.900% | 8.76 h |
| Two in parallel (1-of-2) | 99.9999% | 0.53 min |
1 − (1 − 0.999)² = 99.9999%The calculation assumes the two modules fail independently. In practice common-cause failures — shared switchgear, batteries of the same age, the same maintenance error — usually dominate, so the real gain is smaller than the arithmetic suggests. Treat the parallel figure as an upper bound.
What these show
- Put downtime in money. An availability percentage rarely moves a budget; a cost per period and a what-if comparison usually does.
- Work backwards from targets. An availability commitment implies a maximum repair time — that is the number to write into service contracts.
- Size spares from demand, not habit. Removals per month and repair lead time give a Poisson demand you can stock against a fill-rate target.
- Question redundancy maths. Parallel formulas assume independence; common-cause failures decide how much of the theoretical gain you actually get.